Project

Sanofi Data Center

Location Bridgewater, New Jersey
Completion June 2008
Client Sanofi Avertis
Architect Kling Stubbins Architecture
Services Construction Management
Size 10,000 sf

SOCO Construction was selected as Construction Manager to convert an existing office area to a new main data center that serves multiple campuses. Major equipment installations included new dry coolers on the roof with a structural steel platform, 50-ton CRAC units located in a mechanical corridor adjacent to the data center, 500 kva UPS systems in new electrical support rooms and a new emergency generator. The project was completed on schedule, under budget and with no impact to the adjacent data center that remained in operation throughout construction.